Town of Leland Streets Resurfacing 2021-2022

Town of Leland Streets Resurfacing 2021-2022

To resurface nine streets within the Town limits to include Olde Waterford Way, a portion of Woodwind Drive, Palm Ridge Drive, Old Village Circle, Royal Palm Way, a portion of Pine Harvest Drive, Bentgreen Drive, West Gate Drive, the intersection at New Pointe Boulevard, and the commercial section of Grandiflora Drive. The scope of the project includes milling, full depth patches as needed, and asphalt overlay of those nine streets.

C.M. Mitchell Construction Company, Inc.

Construction Contractor

CLD Engineering, LLC

Engineering and Design

Project Updates

Pine Harvest Drive Sidewalk Work Continues
Tuesday, November 15, 2022

Construction crews are out working on the installation of a new sidewalk along Pine Harvest Drive.  Crews will be forming up the new sidewalk and concrete trucks will be in the area tomorrow, November 16, 2022.  Work will take several weeks to complete.  Traffic will be diverted to one-lane as needed.  Residents should expect delays and use caution when driving in the area.

Construction Continues
Thursday, November 10, 2022

Construction crews will be out on West Gate Drive on Monday, November 14, 2022, moving the storm drain drop inlets from in the middle of the road to the curb line. Work will take several days to complete. Traffic will be diverted to one-lane and directed through the commercial section as needed. Residents should expect delays and use caution when driving in the area.

Pine Harvest Drive Sidewalk
Friday, November 04, 2022

The Town plans to have a contractor out this Monday, November 7, 2022, to begin work on the installation of a new sidewalk along Pine Harvest Drive and demo the existing sidewalk.  Work will take several weeks to complete. Traffic will be diverted to one-lane as needed.  Residents should expect delays and use caution when driving in the area.

Construction Delayed
Wednesday, October 26, 2022

Construction is on hold until the storm drain boxes for West Gate Drive are delivered.  Once these boxes are delivered, the contractor will relocate the two storm drains outside of the roadway and realign the curb along West Gate Drive, then the final asphalt can be placed down and striping along all roads can be completed.  Residents should continue to use caution while driving in areas where the final asphalt has not been put down.

Resurfacing Continues
Wednesday, October 12, 2022

Paving crews are finishing on Grandiflora Drive this morning and will be moving to West Gate Drive this afternoon. Traffic will be diverted to one-lane and directed through the commercial section as needed. Residents should expect delays and use caution when driving in the area.

Resurfacing Grandiflora Drive
Tuesday, October 11, 2022

Paving crews are finishing on Olde Waterford Way this morning and will be moving to Grandiflora Drive this afternoon to resurface the commercial section of Magnolia Greens. Traffic will be diverted to one-lane and directed through the commercial section as needed. Residents should expect delays and use caution when driving in the area.

Resurfacing Olde Waterford Way
Monday, October 10, 2022

Paving crews will be out on Palm Ridge Drive and Olde Waterford Way on Monday, October 10, 2022. Traffic will be diverted to one-lane and directed through the commercial section as needed. Residents should expect delays and use caution when driving in the area.

Resurfacing Continues throughout Waterford
Friday, October 07, 2022

Paving crews will be out on Woodwind West, Palm Ridge Drive, and Olde Waterford Way.  Residents are to expect delays as traffic will be held until the asphalt is cold enough to drive on.  Please use caution when driving in the area.

Resurfacing Continues throughout Waterford
Thursday, October 06, 2022

Paving crews will be out on Pine Harvest Drive, Olde Village Circle, and Woodwind West in the Waterford neighborhood.  Residents are to expect delays as traffic will be held until the asphalt is cold enough to drive on.  Please use caution when driving in the area.

Resurfacing
Wednesday, October 05, 2022

Milling is now complete on all roads and resurfacing has started.  Paving crews will be out on Pine Harvest Drive, Bentgreen Drive, and Olde Village Circle.  Residents are to expect delays as traffic will be held until the asphalt is cold enough to drive on.  Please you caution when driving in the area.