Project includes the construction of a new sewer force main, gravity sewer, and water main along Brunswick Village Boulevard Extension and Kay Todd Road. The project will help serve the developing areas within Brunswick Forest and along Kay Todd Road.
Engineering and Design
Construction Contractor
Project Updates
Kay Todd Road is open to all traffic. The contractor finished installing underground utilities across Kay Todd Road and backfilled the site. There is still small cleanup needed and the contractor plans to pave early next week. Please use caution when in the area.
Due to the rain and severe weather this week, the road closure to all traffic on Kay Todd Road is being extended through 5 p.m. on March 24. All traffic will be detoured into Brunswick Forest, onto Brunswick Forest Parkway, to the water tower, and onto Kay Todd Road.
The Town of Leland will be closing Kay Todd Road to all traffic at 8 a.m. on March 15 and the road will remain closed until 5 p.m. on March 19. All traffic will be detoured into Brunswick Forest, onto Brunswick Forest Parkway, to the water tower, and onto Kay Todd Road.