Olde Waterford Way Extension

Olde Waterford Way Extension

A project to extend Olde Waterford Way from Palm Ridge Drive to Olde Regent Way. This road extension will alleviate traffic congestion along existing Olde Waterford Way and better serve the developing areas within Waterford.

Cape Fear Engineering

Engineering and Design

MSB Development, Inc.

Construction Contractor

Project Updates

Project Close Out
Wednesday, May 31, 2023

Town staff is working with the contractor and engineer to close out the project.

Left Turn Yield
Thursday, April 20, 2023

Reminder Olde Waterford Way Extension from the roundabout at Olde Regent Way to Palm Ridge Drive in the Waterford Residential subdivision is open to all traffic. The Town has put up a message board to warn vehicles to Yield when making a left turn.  Residents are reminded to continue to use caution as there is a new traffic pattern and vehicles coming from the extension have the right of way. 

Olde Waterford Way Extension is Open
Monday, April 10, 2023

Olde Waterford Way Extension from the roundabout at Olde Regent Way to Palm Ridge Drive in the Waterford Residential subdivision is open to all traffic. Residents are reminded to use caution as there is a new traffic pattern as you come into Waterford and vehicles coming from the extension have the right of way. 

Barricades
Friday, March 03, 2023

Town Staff will be installing water filled barricades this afternoon at the entrances to the newly constructed Olde Waterford Way Extension.  Residents are reminded to not move the barricades as the site is still under active construction.  Thank you for your patience as we work to complete the project.

Striping is Complete
Wednesday, March 01, 2023

Striping is complete on Olde Waterford Way Extension and the roundabout at Olde Regent Way.  Streetlights are currently being installed along the new roadway.  The contractor is working to fix a ponding concern and complete final punch list items before the road can be open to the public.  Please continue to use caution when driving in the area.

Striping Installation
Tuesday, February 14, 2023

The contractor installed the majority of striping along the roadway extension. The contractor is waiting for material to arrive to install the fish-hooks within the Olde Regent Way roundabout.

Start of Paving
Thursday, January 05, 2023

The contractor has begun paving the roadway. Paving is anticipated to be completed within a week.

Prepping for Installing Pavement
Thursday, December 29, 2022

The contractor has compacted and fine graded the roadway to prepare for installation of pavement.

Sidewalk Installation Complete
Tuesday, November 29, 2022

The contractor has completed installing sidewalk. The contractor plans to start paving and installing pavement markings the first week of December.

Installation of Sidewalk
Thursday, November 17, 2022

The contractor is continuing to install curb and gutter and has begun pouring sidewalk.

Project Documents

Construction Drawings
Olde Waterford Way Construction Drawings
Public Meeting FAQ
Olde Waterford Way Public Meeting FAQ