Sturgeon Creek Park

Sturgeon Creek Aerial

The currently undeveloped Sturgeon Creek Park is intended to serve as Leland’s second water access park. With more than 78 acres, this park has the potential to become a destination facility both locally and regionally for sportsmen and water lovers wishing to gain access to Sturgeon Creek and the Brunswick River. Sitting on Sturgeon Creek, the focus for this facility will be boating access from an NC Fish and Wildlife boat ramp as well as environmental education, preservation, and nature-based activities. Town Council adopted the Master Plan at its Feb. 2020 regular meeting. Next steps for the project will be to move forward with engineering when additional funding is available.

North Carolina Wildlife Resources Commission

Boat Ramp Design & Construction 

Withers Ravenel

Engineering Firm-Environmental Consultant

Project Updates

Boat Ramp Design
Tuesday, July 23, 2024

With the boat ramp preliminary, concept design completed, next steps for the project will involve holding a scoping meeting with CAMA and other stakeholders to get approval to continue with design.  This meeting is expected to happen within the next 2 months, however an official date has not yet been determined.

Underground Storage Tank Investigation
Thursday, June 27, 2024

Through environmental testing, there were several areas of the site identified as possibly having underground storage tanks, which would need removal.  The Town has completed investigation of these areas and confirmed that there were no underground tanks present.  

Prelim Boat Ramp Plans
Wednesday, June 05, 2024

The Town has received preliminary site plans for the construction of a NC Wildlife Resource Commission boat ramp, which will be Phase 1 of the overall park project.  Next steps include holding a scoping meeting with WRC, CAMA, and other stakeholders to determine is the proposed plan will meet all requirements necessary to move forward with the design and future construction.  

Environmental Testing Completed
Monday, April 01, 2024

As part of the Brownfields Program, environmental testing was required for multiple parcels in the future Sturgeon Creek Park.  Testing has been completed and NCDEQ is currently working on a final Brownfields report which establishes as future work plan that must be adhered to in regard to future development. 

Environmental Testing Reports Received
Thursday, February 29, 2024

The Town has received reports relating to enviromental testing as part of the ongoing Brownfields program.  We are expecting to receive the completed Brownfields report by July 2024 and will coincide with the design of the public boat ramp by NC Wildlife.

Town has received grant funding for completion of Brownfields Study
Friday, September 01, 2023

The Town has partnered with NCDENR and EPA to secure grant funding for the completion of the Brownfields Study.  This funding includes environmental field testing and administrative work associated with completing the Brownfields agreement.  Testing is currently in progress.

NCDENR Project Manager Assigned for Brownfields Study
Friday, April 28, 2023

The Town has been assigned a project manager through NCDEQ to begin work on the Brownfields Study.  This PM will work closely with the Town, as well as, the Town's contracted engineer to develop a workplan to address environmental concerns on the property.  This process is expected to take at least a year to complete and gain full approval.

Brownfields Study
Thursday, January 05, 2023

The Town is awaiting direction from NCDENR on next steps related to a Brownfields Study of park property.  After the study is complete, the Town will receive guidelines for construction based on the findings.  These guidelines will be followed as part of the boat ramp construction project.  

Boat Ramp Design
Tuesday, June 28, 2022

Pre-planning is currently underway with NC Fish and Wildlife for the design and construction of the boat ramp, which is a key element to Phase 1 of the Sturgeon Creek plan.